A chimney inside the house must have at least 2” (50mm) of clearance to the combustible structure. A chimney
outside the house must have at least 1” (25mm) clearance to the combustible structure. Firestops must be
installed in the spaces where the chimney passes through floors and/or ceiling (Figure 5).
The chimney must have a fire clay flue liner (or equivalent) with a minimum thickness of 5/8” (16mm) and
must be installed with refractory mortar. There must be at least ½” (13mm) air space between the flue liner and
the chimney wall (Figure 4). An equivalent liner must be a listed chimney liner system or other approved
material.